Every property manager who has filed with the Department of Buildings knows the specific feeling of a project stalling for a reason nobody can explain. The permit is “in examination.” The QEWI’s report has been sitting for six weeks. The shed permit expires in eleven days and the work permit hasn’t been issued. Nobody in the chain will give you a date.
Most of that friction is structural, and most of it is predictable. NYC DOB permits and FISP inspections run on defined sequences with defined dependencies, and the delays cluster in the same four places on nearly every job. This guide maps the sequence end to end, what triggers which filing, who can sign what, how a facade inspection converts into a work permit, and what the 2026 rule changes did to the timeline. For the broader project context, our Manhattan commercial construction and building restoration playbook covers how permitting fits into the full arc of a building program.
Two systems, one building: FISP and permits are different tracks
FISP is a reporting obligation. A DOB permit is an authorization to perform work. They connect, but they are separate filings on separate timelines through separate DOB modules. A building can be fully FISP-compliant and have no permits. A building can hold permits and be delinquent on FISP. And critically, filing an acceptable FISP report does not authorize the repairs that report requires.
| FISP | DOB work permit | |
| What it is | A condition report on the exterior wall | Authorization to perform construction |
| Who files | QEWI (NYS-licensed PE or RA, DOB-registered) | Registered design professional or licensed contractor |
| Module | DOB NOW: Safety | DOB NOW: Build |
| Triggered by | Your building’s cycle window | Scope of work |
| Frequency | Cyclical | Per project |
FISP: the inspection side
Who has to comply? Buildings taller than six stories, in all five boroughs, residential, commercial, institutional and mixed-use alike.
Your filing window is set by your block number. Cycle 10 runs on three staggered sub-cycles keyed to the last digit of your tax block number:
| Sub-cycle | Block number ends in | Filing window |
| 10A | 4, 5, 6, 9 | Feb 21, 2025 – Feb 21, 2027 |
| 10B | 0, 7, 8 | Feb 21, 2026 – Feb 21, 2028 |
| 10C | 1, 2, 3 | Feb 21, 2027 – Feb 21, 2029 |
Look up your block number before anything else. Managers inherit buildings and inherit assumptions about which cycle they are in, and the assumption is wrong often enough to be worth thirty seconds of verification.
Who can perform the inspection? Only a Qualified Exterior Wall Inspector, a Professional Engineer or Registered Architect licensed in New York State and registered with the DOB for this purpose. Your general contractor can’t file it. Your architect can’t file it unless separately QEWI-registered. The QEWI carries personal professional liability for the filing.
What the inspection physically involves. Hands-on, close-up inspection along street-facing and public-right-of-way-facing facades, at intervals of every 60 feet of street-facing wall. Other elevations may be observed with high-powered binoculars. Reports require photographic documentation and, frequently, annotated markups. Access is typically by swing stage, boom lift or rope access, which is why the access equipment, not the engineer’s time, is usually the larger line item.
Published NYC ranges put FISP inspection costs at roughly $8,000–$20,000 for six to twelve stories. $20,000–$60,000 for larger or more complex buildings. Current DOB filing fees run $425 for an initial report, $425 for amended or subsequent reports, and $305 for a 90-day extension.
The three classifications, and what each one obligates you to do
SAFE: No unsafe or SWARMP conditions. Routine maintenance recommended. No further DOB action this cycle.
SWARMP, Safe With A Repair and Maintenance Program: Conditions that aren’t an immediate hazard but will become one. Each condition carries a repair deadline stated in the report. Two things managers routinely underestimate: the repair deadline is enforceable, with a $2,000 penalty for failure to correct by the stated date; and an uncorrected SWARMP condition is likely to be filed as Unsafe at the next cycle.
Think of SWARMP as a debt with a due date, not a footnote. It gets treated as a footnote because it arrives with no immediate consequence, which is exactly why it produces the expensive surprise one cycle later.
UNSAFE. Conditions presenting an immediate hazard. This one moves fast:
1. Public protection, typically a sidewalk shed, must go up immediately, and the DOB may inspect within 24 hours of notification.
2. Repairs must be completed on a short DOB-mandated schedule. Published guidance varies between 30 and 90 days depending on the condition and the report; confirm the deadline stated in your own report rather than relying on a general figure. A 90-day extension can be applied for, currently at a $305 filing fee.
3. An amended report must be filed within two weeks of repair completion.
4. Failure to correct accrues fines of $1,000+ per month, on top of shed carrying costs.
| Failure | Penalty |
| Failure to file a FISP report | From $1,000/month |
| Late filing | Commonly $250 – $1,000 |
| Annual failure to file | $5,000 |
| Unsafe condition not corrected | $1,000/month plus shed costs |
| SWARMP not corrected by deadline | $2,000 |
The 2026 rule changes every property manager needs loaded
Local Law 47 (Aug 15, 2025): Minimum sidewalk shed clearance raised from 8 ft to 12 ft, with revised design standards.
Local Law 50 (Aug 15, 2025): Brighter LED lighting required under every shed in the city, including sheds already standing. Expect a compliance cost on existing installations, not just new ones.
Local Law 48 (Jan 12, 2026): New shed permits capped at 90 days, no automatic renewal. Every renewal is a manual application in DOB NOW: Build. From the second renewal forward, a registered design professional must certify that work has been performed since the last renewal. Monthly penalties of $10 to $200 per linear foot accrue where progress can’t be demonstrated. All outstanding DOB penalties on the property must be cleared before a shed permit will renew.
Local Law 51 (Jan 12, 2026): Hard deadlines once a shed is up: construction documents within 5 months, an acceptable work permit within 8 months, repairs complete within 24 months. Penalties of $5,000 to $20,000 for sheds standing without repair progress.
Local Law 49 (Oct 1, 2026): The fixed five-year FISP interval is replaced by a range of six to twelve years. New buildings file their first report at year eight rather than year five.
What this stack means operationally
One, clear your violations before you need a shed: Under Local Law 48, outstanding DOB penalties block shed permit renewal. A $1,200 unrelated violation nobody got around to resolving can now stop a renewal on a shed protecting the public, which escalates fast. Run a clean violation report quarterly.
Two, the 5/8/24 clock starts at shed erection, not at permit approval: Manager after manager builds a schedule backward from the repair, assuming filing time is free. If construction documents are due five months after the shed goes up. Plan examination on a complex ALT2 can run several weeks with objections, the design work needs to be substantially underway before the shed is erected.
Three, Local Law 49’s longer cycle increases your internal inspection burden, not decreases it: Six to twelve years between mandatory inspections means more deterioration between official looks. Buildings that don’t run voluntary assessments between cycles will meet the DOB again at a worse classification.
DOB permits: which filing does your scope trigger
| Type | What it covers | Plan examination | Typical timeline |
| ALT1 | Changes to use, egress or occupancy, new Certificate of Occupancy required | Always | 2–8 weeks, longer with objections |
| ALT2 | Multiple work types, no change to use or egress, most gut renovations and facade programs | Sometimes; may qualify for professional certification | Days if self-certified; weeks if examined |
| ALT3 | One minor work type, a single plumbing fixture, minor partition work | Rarely | Days |
| LAA | Limited alterations, sidewalk sheds, fences, signs, curb cuts, solar | No | Days |
| NB | New building | Always | Longest |
| DM | Full or partial demolition | Yes | Varies |
| Trade permits | Plumbing, electrical, mechanical, filed by licensed trades | Varies | Parallel track |
Filing fees run roughly $250–$2,000+ for ALT1, $150–$500 for ALT2 and ALT3, and $100–$300 for LAA filings.
Facade restoration is typically an ALT2, with a separate LAA for the sidewalk shed. An interior fit-out that relocates an egress stair or changes occupancy classification becomes an ALT1, and ALT1 always goes through plan examination, which is the difference between a permit in days and a permit in months.
The classification trap. The costly error is filing a project as an ALT2 that is legally an ALT1. It surfaces at plan examination or, worse, at Certificate of Occupancy, after the work is built. Refiling mid-project means new drawings, new examination and a stalled site with carrying costs running. Any scope touching egress, occupancy classification, occupant load or use should be reviewed for ALT1 triggers before a filing strategy is set.
The full sequence: from QEWI report to shed removal
1. QEWI inspection: access equipment mobilized, hands-on inspection at 60-foot intervals on street-facing walls, photo documentation.
2. Report filed in DOB NOW: Safety: classification assigned: Safe, SWARMP or Unsafe.
3. If Unsafe: public protection erected immediately: this starts the Local Law 48 90-day permit clock and the Local Law 51 5/8/24 clock simultaneously.
4. Design and construction documents: due within 5 months of shed erection.
5. ALT2 filing in DOB NOW: Build: plan examination or professional certification.
6. Objections resolved: the most common and least predictable delay in the sequence.
7. Work permit issued: due within 8 months of shed erection.
8. The contractor mobilizes: hoisting, rigging, protection, sequencing.
9. Repairs performed: complete within 24 months of shed erection.
10. Sign-offs, re-inspection and amended FISP report filed.
11. Shed permit closed and shed removed.
Where the four delays actually happen
Between steps 2 and 4, the design gap. The report lands, everyone reads it, and then two months pass before an engineer is engaged. The most common and most avoidable delay in the sequence, and under Local Law 51 it now consumes most of a five-month statutory deadline.
At step 6, objections. Incomplete drawings, zoning inconsistencies, missing structural documentation, unresolved egress questions. Each objection round costs weeks. The fix is front-loaded quality control on the filing, not faster responses afterward.
Between steps 7 and 8, contractor procurement. If bidding starts after the permit is issued, weeks of permit time are burned on a process that could have run in parallel with plan examination.
At step 10, sign-off administration. Sign-offs, inspections and the amended FISP filing get treated as paperwork after the “real work” is done. The shed stays up through all of it, at $40–$100 per linear foot per month, and under Local Law 48 that shed permit still needs renewing every 90 days.
Compressing this sequence is mostly a matter of running steps in parallel that most teams run in series. Design can begin before the report is formally filed if the QEWI’s findings are known. Bidding can run during plan examination. Sign-off documentation can be assembled during construction rather than after it. What that scope actually involves in the field is covered in what facade deterioration actually costs to repair.
Beyond FISP: the rest of the commercial compliance calendar
Local Law 126 parapet observations, annual, due December 31. Required for any building with a parapet fronting a public right-of-way, regardless of height; fully detached one- and two-family dwellings are the principal exemption. The observation may be performed by a “qualified person” with relevant construction knowledge rather than strictly a PE or RA, but a report from a licensed engineer or architect carries considerably more weight if the parapet later fails. A DOB observation checklist must be completed with annotated photographs organized by building side, pass/fail determinations per parapet section and repair recommendations. Records were retained for six years. No DOB filing required unless a hazardous condition exists. Published guidance places ECB penalty exposure between roughly $1,250 and $10,000, with the lower figure commonly cited for failing to produce a report on DOB request. Schedule this before September so any hazard found can be corrected within the same calendar year.
Elevator inspections: CAT1 no-load safety test annually, CAT5 full-load test every five years, plus annual periodic visual inspection. All due December 31.
Boiler inspections: annual combustion efficiency testing and certification, DOB filing finalized by December 31.
Local Law 152 gas piping: four-year cycle by community district.
Local Law 84 benchmarking: annual, due May 1, for buildings 25,000 SF and above. Late submission penalties start at $500 per month.
Local Law 87 energy audit: ten-year cycle keyed to tax block last digit.
Local Law 97 emissions: annual reporting for buildings 25,000 SF and above.
Run all of these on one calendar per property, with owners assigned and a 60-day advance reminder on each. The failure mode is never that a manager didn’t know the requirement — it is that nobody owned the date.
Frequently asked questions
Can my general contractor file my FISP report?
No. FISP reports must be filed by a Qualified Exterior Wall Inspector, meaning a Professional Engineer or Registered Architect licensed in New York State and separately registered with the DOB. Your contractor performs the repairs the report identifies; a QEWI determines and files the condition of the wall. Some firms maintain a QEWI relationship to coordinate the handoff, but the roles remain legally distinct.
How long does a DOB permit take in NYC?
It depends on the type of filing. An LAA or professionally certified ALT3 can be issued in days. A plan-examined ALT1 or new building filing typically runs two to eight weeks, and materially longer when objections are issued. The variable you control is filing quality, most delays in NYC permitting are objection rounds, not queue time.
What happens if my sidewalk shed permit expires?
An expired shed permit produces ECB violations with fines reaching $8,000 per violation, and the shed is still legally required if the underlying condition remains unsafe. Under Local Law 48, permits run 90 days with no automatic renewal, renewals after the first require a design professional to certify work has been performed, and outstanding DOB penalties must be cleared before renewal is granted.
Does a SWARMP finding require immediate repairs?
Not immediately, but not indefinitely either. Each SWARMP condition carries a repair deadline stated in the QEWI’s report, and failure to correct by that date carries a $2,000 penalty. The larger risk is the next cycle: uncorrected SWARMP conditions commonly get reclassified as Unsafe, which triggers a sidewalk shed and the 5/8/24-month statutory schedule under Local Law 51.
Do we still file FISP every five years after Local Law 49?
Not on a fixed five-year interval. From October 1, 2026, Local Law 49 replaces the fixed cycle with an interval between six and twelve years, and new buildings file their first report at year eight. Existing Cycle 10 sub-cycle windows still govern current filings, so confirm your building’s assigned window rather than assuming the new interval applies to a filing already in progress.
What is the difference between DOB NOW: Build and DOB NOW: Safety?
DOB NOW: Build handles permit applications, job filings, plan approvals and work permits for construction, alteration and demolition. DOB NOW: Safety handles compliance filings, FISP facade reports, elevator and boiler certifications, and related safety submissions. A facade restoration touches both.
Who is responsible for compliance, the owner or the property manager?
Legal responsibility sits with the building owner. DOB violations and penalties are issued against the property and the owner of record. Property managers carry operational responsibility under their management agreement, which is why documented compliance calendars, retained inspection records and written notice of upcoming deadlines matter as much for the manager’s protection as for the building’s.
The practical takeaway
Almost every expensive DOB outcome traces back to one of three things: a classification error at filing, a gap between the inspection report and the design work, or a shed that outlived the schedule around it.
All three are avoidable with the same discipline, know your window, start design before you need it, and treat the filing sequence as a project plan rather than paperwork. The penalty amounts here are real, but they are rarely the largest cost. The largest cost is a building sitting under a shed, in examination, with a leasing agenda on hold.